The works hand-over took place on Friday 22nd January. 

A snagging list has been completed by the architect which is fairly extensive.  The contractor started this on Monday 8th February.

Some exterior walls have to be re-harrled and the contractors are to come back to complete this work. 

The car park white lining is to be done and we will create at least one more disabled car parking space.

The window which was blocked up in the Pro Shop now has a display board on the exterior which looks much better.

The honours boards, past captains pictures, painitngs etc.,  have still be repositioned.  It looks like we will have new honours boards to replace the old ones.  A small sub-committe has been formed to look at how best to utilise the space in the foyer area.

It is intended to have a official re-opening following refurbishment after the Opening Competition - on 27th March 2010.

    
 
 